Building Permit Review Schedule
Below is the building permit review schedule for building permit applications in Centennial. This outlines the expected business days for each of the different types of permits to ensure timely approval.
One-Stop Permits - for air conditioner, furnace, water heater, electric service change, gas line, irrigation line, miscellaneous reroof windows/doors is one business day.
New Build Commercial - for additions, multi-family permits, residential master plans is 20 business days after the plan review fee is paid.
Commercial Permits - alterations, low voltage, miscellaneous, renewable energy, temporary or accessory structure, tenant improvement is 10-15 business days after the plan review fee is paid. Stand-alone demolition permits is two business days.
Multi-Family Permits - alterations, demolition, low voltage, miscellaneous, renewable energy and temporary or accessory structure is 10-15 business days after the plan review fee is paid.
New Build Residential - (including additions permits) is 10-15 business days after the plan review fee is paid.
Residential Permits - alterations, demolition, miscellaneous, new, renewable energy, and temporary or accessory structure is five business days after the plan review fee is paid.
Additional Information
Timelines for first comments begin upon receipt of a complete submittal.
The review of re-submittals and revisions may take up to 10 business days.
Pre-submittal meetings are highly encouraged by staff at the City of Centennial (for any size/type of project) in order to ensure that all interested parties are given the opportunity to obtain and discuss City policies and guidelines.
To schedule a pre-submittal meeting, please contract the Building Division at 303-754-3321.